top of page


Construction Update: November 5, 2025
Dear Neighbors,  Last week, the 160 Freelon construction team reached an exciting milestone by successfully completing the concrete pour for the project’s mat slab. The mat slab will serve as the solid first-floor foundation that will support future construction. Thank you for your patience while the construction team’s crews worked hard to complete this work as quickly and with as little disturbance as possible.  Now, the site will begin to rise vertically. The constructi
Nov 5


Construction Update: October 14, 2025
Dear Neighbors, This past week, the construction team, Cahill Guzman Joint Venture, continued progress on the first-floor mat slab. Crews are continuing to install rebar, piping, and formwork through the end of the week in preparation for the Saturday, October 25 mat slab pour. This will be one of the project’s largest pours—approximately 2,000 cubic yards of concrete placed in a single day. To allow the concrete to dry over the course of the day, this work is scheduled betwe
Oct 14


Construction Update: October 10, 2025
Dear Neighbors, We’d like to share an update on recent construction activities at 160 Freelon. This past week (October 5–October 11), the construction team, Cahill Guzman Joint Venture, continued progress on the first-floor mat slab. The waterproofing and vapor-mitigation membrane are now complete, and formwork is in place. Electricians and plumbers have been installing conduit and piping within the mat slab. A mobile crane will be on site Monday, October 13, to assist with s
Oct 10
bottom of page