Construction Update: January 6, 2026
Dear Neighbors, The fifth concrete pour is well underway, and crews have been working on a schedule set to help protect the structure from wet weather. Last week, our team made strong progress completing the fifth-floor walls and columns and preparing the sixth-floor deck, with work expected to conclude smoothly as conditions allow. Now, as the new year begins, the construction team, Cahill Guzman Joint Venture, is continuing work on the sixth-floor deck and finishing key w
Jan 6


Construction Update: December 10, 2025
Dear Neighbors, This past week, the construction team placed the third-floor slab, walls, and columns. On the fourth floor, decking is now complete; layout work, edge forms, and embeds are in progress. Looking ahead, the fourth-floor concrete pour is scheduled for Thursday, December 11, beginning at 7:00 AM. Depending on temperatures and concrete delivery, the pour may continue until sundown. Neighbors will be notified if any delays occur. What This Means for You Scaffold
Dec 10, 2025


Construction Update: November 5, 2025
Dear Neighbors, Last week, the 160 Freelon construction team reached an exciting milestone by successfully completing the concrete pour for the project’s mat slab. The mat slab will serve as the solid first-floor foundation that will support future construction. Thank you for your patience while the construction team’s crews worked hard to complete this work as quickly and with as little disturbance as possible. Now, the site will begin to rise vertically. The constructi
Nov 5, 2025