top of page


Construction Update: March 10, 2026
Dear Neighbors, Construction is moving steadily upward and around the site. This week (March 8–14), Cahill Guzman Joint Venture placed equipment pads and curbs on the roof and started removing the temporary supports below. Scaffolding on the south side is now above the roof and netted, and crews are continuing to raise scaffolding around the building, including on the east side. Exterior framing is now up to the 6th floor, and interior work on the lower floors is wrapping u
6 hours ago


Construction Update: February 3, 2026
Dear Neighbors, Construction continues to move upward on the site. During the week of January 26, our construction team, Cahill Guzman Joint Venture, completed work on the seventh floor. Since then, crews have progressed on the eighth floor by pouring the concrete floor surface and building the walls along the south and north side. With this progress, preparations are underway to begin work on the ninth floor, which will be the final level before the roof. The ninth-flo
Feb 3


Construction Update: January 6, 2026
Dear Neighbors, The fifth concrete pour is well underway, and crews have been working on a schedule set to help protect the structure from wet weather. Last week, our team made strong progress completing the fifth-floor walls and columns and preparing the sixth-floor deck, with work expected to conclude smoothly as conditions allow. Now, as the new year begins, the construction team, Cahill Guzman Joint Venture, is continuing work on the sixth-floor deck and finishing key w
Jan 6
bottom of page