top of page


Construction Update: September 8, 2026
Dear Neighbors, We'd like to share an update on recent construction activities at 160 Freelon, where the project continues to move through its finishing stage. On the exterior, scaffolding has been removed from the first-floor perimeter, and crews are continuing work on the building's final water line connection along Freelon Street. Stucco work has also begun along the southeast façade, with additional caulking, painting, storefront installation, and play yard improvements
Sep 8


Construction Update: September 3, 2026
Dear Neighbors, We'd like to share an update on recent construction activities at 160 Freelon, where the project has moved into its finishing stage. On the exterior, the construction team has been working from a suspended platform along the east side of the building to close up the openings left behind by the scaffold beams. Once that section is finished, the platform will move to the north end of the east-facing wall to complete the same work there. We also removed the scaff
Sep 3


Construction Update: March 10, 2026
Dear Neighbors, Construction is moving steadily upward and around the site. This week (March 8–14), Cahill Guzman Joint Venture placed equipment pads and curbs on the roof and started removing the temporary supports below. Scaffolding on the south side is now above the roof and netted, and crews are continuing to raise scaffolding around the building, including on the east side. Exterior framing is now up to the 6th floor, and interior work on the lower floors is wrapping u
Mar 13
bottom of page