Construction Update: December 10, 2025
Dear Neighbors, This past week, the construction team placed the third-floor slab, walls, and columns. On the fourth floor, decking is now complete; layout work, edge forms, and embeds are in progress. Looking ahead, the fourth-floor concrete pour is scheduled for Thursday, December 11, beginning at 7:00 AM. Depending on temperatures and concrete delivery, the pour may continue until sundown. Neighbors will be notified if any delays occur. What This Means for You Scaffold
6 days ago


Construction Update: November 5, 2025
Dear Neighbors, Last week, the 160 Freelon construction team reached an exciting milestone by successfully completing the concrete pour for the project’s mat slab. The mat slab will serve as the solid first-floor foundation that will support future construction. Thank you for your patience while the construction team’s crews worked hard to complete this work as quickly and with as little disturbance as possible. Now, the site will begin to rise vertically. The constructi
Nov 5


Construction Update: October 14, 2025
Dear Neighbors, This past week, the construction team, Cahill Guzman Joint Venture, continued progress on the first-floor mat slab. Crews are continuing to install rebar, piping, and formwork through the end of the week in preparation for the Saturday, October 25 mat slab pour. This will be one of the project’s largest pours—approximately 2,000 cubic yards of concrete placed in a single day. To allow the concrete to dry over the course of the day, this work is scheduled betwe
Oct 14